The 405 Repave Spent the Fall Right Under Mulholland. What's Left Before It Wraps?

The equipment for the I-405 repave sits in the Skirball Yard, the contractor yard off Mulholland Drive near American Jewish University. When the project began in summer 2025, that yard was the closest the work came to the hillside. The paving started down by Wilshire and Sunset, miles from the cul-de-sacs off Mulholland. Over the past year it has climbed the pass. On four weekends this fall, September 11–14, September 25–28, October 2–5 and October 23–26, southbound I-405 dropped to three lanes between Ventura Boulevard and Mulholland Drive. That is the stretch directly below the ridge.

If you live in Stoneridge Estates, the work has spent most of the past year on the part of the freeway you actually use. On the schedule, though, most of the project is now behind it.

A Project That Worked Its Way Uphill

The $143.7 million Interstate 405 Sepulveda Pass Pavement Rehabilitation Project covers 10.2 miles between Van Nuys and Westwood. The heaviest work is replacing sections of two lanes in each direction from Victory Boulevard to Mulholland Drive. It is a repave and nothing more. Caltrans says there is no widening and no new sound walls.

The best way to see where the work has been is to follow the extended weekend lane reductions through Caltrans District 7's own announcements. Each one ran from 10 p.m. Friday to 5 a.m. Monday. The work moves steadily north.

Period Direction Where the lanes narrowed
Aug.–Oct. 2025 Both Santa Monica Blvd. to just north of Sunset; north of Sunset to Wilshire
Dec. 2025–Mar. 2026 Both Northbound from Getty Center Drive to Bel Air Crest Road; southbound from the Skirball Center Drive/Mulholland on-ramp to Getty Center Drive
April 2026 Northbound Skirball Center Drive to Ventura Blvd.
May–June 2026 Northbound Mulholland Drive to U.S. 101
July 2026 Southbound Through the U.S. 101 connectors
Sept.–Oct. 2026 Southbound Ventura Blvd. to Mulholland Drive

There is one exception to the northward march. The January 30–February 2 weekend went back to the Wilshire-to-Sunset segment. Otherwise, every period since December 2025 has touched the miles between Getty Center Drive and the Valley floor. The December weekends closed the southbound on-ramp at Skirball Center Drive and Mulholland, the ramp closest to the ridge. In February and March, the southbound lane reductions started at that ramp. In June, northbound I-405 also had two short overnight full closures just south of Ventura Boulevard, early on June 6 and June 8.

Counting the Weekends

Caltrans planned about 25 extended weekend lane closures for the whole project. These are lane reductions with at least two lanes left open in each direction, not 55-hour full closures. Count the weekends District 7 has put on its schedule since August 2025 and you get 21:

  • 2025: August 22, September 5, September 19, October 17, December 5 and December 19
  • 2026: January 9, January 30, February 6, March 20, April 17, May 1, May 15, May 29, June 5, July 17, July 24, September 11, September 25, October 2 and October 23

If the original plan holds, that leaves about four. Caltrans has moved dates often, though, so treat the count as a rough guide. The August 8–11, 2025 weekend slid to August 22. The November 14–17, 2025 weekend moved to December 5–8. December 12–15 became December 19–22, March 13–16 became March 20–23, and the April 10–13 weekend was postponed because of weather. Last year, the closure planned for mid-November ended up in December. Caltrans also says the project follows construction moratoriums around state holidays and special events.

The Ramp That Keeps Closing

One closure has shown up more consistently than any segment. The northbound off-ramp to Getty Center Drive has been listed as closed on almost every extended weekend since October 2025. That includes the October 2025 weekend, December, January 30, February, March, April, May 29, June, both July weekends, and all four southbound weekends this fall. In September and October it was closed even though northbound lanes were not reduced.

The southbound weekends this fall followed their own pattern, with the same three ramps closed every time:

  • Ventura Boulevard on-ramp to southbound I-405
  • Southbound off-ramp to Valley Vista Boulevard/Sepulveda Boulevard
  • Valley Vista Boulevard/Sepulveda Boulevard on-ramp to southbound I-405

Coming home from the Valley on a closure weekend, the Getty Center Drive exit has usually been unavailable. Leaving the hill southbound from the Sherman Oaks side meant the Ventura and Valley Vista entrances were closed. Caltrans says it can close consecutive on- and off-ramps during the 55-hour weekends to cut the total number of weekends, but it doesn't usually do that on weeknights. Its target is to keep weekend delays within 30 minutes of normal traffic, and weeknight overnight delays within 15 minutes.

Closer Than the Freeway: The Yard on Mulholland

The freeway closures are temporary. The contractor yard is there for the whole project. The CA Rasmussen, Inc. and FBD Vanguard Construction, Inc. joint venture keeps its equipment and materials at the Skirball Yard. Caltrans says the site may hold a batch plant. On regular workdays, the project expects no major trucking between 6 and 9 a.m. or between 5 and 7 p.m. Outside those windows, nearby residents can expect backup alarms and truck activity, with traffic lookouts posted while trucks go in and out.

For someone driving Mulholland near the Skirball, that sets the rhythm of the day. Morning and evening commutes stay clear of yard trucks. Midday and evening errands are when you're likely to meet them. Overnight, Caltrans says contractor noise between 10 p.m. and 6 a.m. will comply with maximum allowed levels at 50 feet, and it will monitor noise throughout construction. On weeknights, the usual overnight lane closures run about 9 p.m. to 6 a.m., and many are limited to 11 p.m. to 5 a.m. The project also includes about 15 to 20 brief full overnight closures between midnight and 5 a.m.

The 55 mph Stretch and the Finish Line

The change you notice every day, closure or not, is the speed limit. Since May 26, 2026, parts of I-405 through the pass have been posted at 55 mph, with "Uneven Pavement" signs between Wilshire Boulevard and Victory Boulevard. The reduction started on the southbound side and moves to the northbound side as paving continues, working from Wilshire toward Victory. Caltrans expects the lower limit and the uneven pavement to last through winter 2026 or early spring 2027.

Construction is projected to finish in winter 2027, with plant establishment continuing into 2028. That landscaping work includes irrigation and planting at points along the corridor. About 13 trees are being removed to build two maintenance vehicle pullouts. Caltrans says it will not postpone the project, because pausing would mean paying the contractor for idle days. It also lists the pauses already set, including moratoriums for the 2027 Super Bowl and a three-month stop in summer 2028 for the LA28 Games.

After that, the next 405 project on the calendar is a different one. Metro's I-405 ExpressLanes project, which would turn carpool lanes into priced toll lanes between Sherman Oaks and Rancho Park, can't start construction before 2029. Caltrans says the two projects are not scheduled to overlap.

Seeing the Next Closure Before It Hits

District 7 posts every extended weekend on its news page, with lane counts and a ramp-by-ramp list. Recent announcements have used the title "Caltrans Announces Southbound I-405 Lane Reductions Through the Sepulveda Pass" or its northbound version, followed by the month. Anyone can sign up for the project's weekly construction emails, which cover overnight and weekend work. For live ramp status, Caltrans updates QuickMap as crews call in each closure. Questions go to [email protected].

For a hillside home off Mulholland, freeway access is part of what a buyer is paying for, and a project with a known end date reads very differently from one with no end in sight. If you're wondering how this stretch of construction affects your property's value today, or how to time a sale around a winter 2027 finish, Mark Kojac can walk you through the numbers. Start with a free home valuation.